AQW 8527/08 Written question to the First Minister and deputy First Minister

To ask the Office of the First Minister and deputy First Minister to outline all its expenditure on the redevelopment of the Maze/Long Kesh site.

Asked by Naomi Long MLA on 24 June 2008

  • Answered
  • Written
Tabled
24 June 2008
Answer due by
8 July 2008
Answered
3 July 20089 days after tabling
Department
The Executive Office
Priority question
No

Answer

Expenditure from 2003 to date on the potential Maze/Long Kesh (MLK) regeneration totals £8million.

Of this total, £4.6 million (over 57%) has been spent on site preparation and management which is required irrespective of any specific development on the site.

The expenditure specified does not include costs incurred by the Strategic Investment Board (SIB) or by the Department of Culture Arts and Leisure (DCAL) in relation to the site. OFMDFM staff costs are not included.

A detailed breakdown of OFMDFM expenditure to date on the site is as follows.

Maze/Long Kesh Expenditure to date (25 June 2008)

SITE PREPARATION AND MANAGEMENT COSTS
Costs incurred for remediation and removal of contamination, demolition works and maintenance of MLK land and buildings.
DescriptionCost millions
Site Management, security and utilities0.5
Listed building maintenance and repair0.3
Demolition and remediation2.7
DFP Central Procurement Directorate advisory fees on works and contracts0.7
Initial site feasibility study0.4
Total (Million)£4.6
MLK
PROGRAMME COSTS
Costs specific to MLK Masterplan and development of proposals.
DescriptionCost millions
Consultation Panel/Monitoring Group0.1
DFP Central Procurement Directorate advisory fees; Programme management0.3
Preparation of business case0.5
Infrastructure design and pre-planning approval & related work1.9
Masterplan development0.6
Total (Million)£3.4
Overall Total£8.0
million